The maximum sprint planning is 8 hours for a 1 month sprint, should it then be 4 hours for a 2 week sprint?
Channel | Publish Date | Thumbnail & View Count | Download Video |
---|---|---|---|
Publish Date not found | 0 Views |
Take this free online course on Scrum https://www.udemy.com/course/scrum-guide-roles-events-artifacts/?referralCodeC156F50A1040E1AABA35
——–
Sprint planning is limited to a maximum of 8 hours for a one-month sprint. For shorter sprints, the event is usually shorter.
Scrum says NOTHING about whether for sprints less than a month the maximum duration of the event should be PROPORTIONALLY shorter. There is no such thing as /"no more than 4 hours are required for a 2-week sprint/".